Manor on the Green - An Update from The Whitmore Company
Posted on September 1, 2023 6:55 AM by Town Crier Staff
 
Note: Manor on the Green is the new 106-unit apartment complex being built adjacent to Sullivan Square. The following information has been provided to the NTRA Board President from the Vice President of Construction for the Whitmore Company.
 
Manor on the Green, scheduled to be completed fall of 2024, is moving along presently with sitework, including the concrete pours to support vertical construction of the buildings. Our intent was to get as much of the site utilities, including water and sewer connections in the streets along with stone for the parking lot, completed prior to the installation of the building foundations. Due to the limited space available onsite, completion of these site items early allows for construction parking and storage of materials in the future parking lot as the work continues with the buildings. 
 
Framing is now underway. The contractor, Henderson Inc. has been asked to walk the property edge and parking areas to look for trash. They are doing this daily to keep the site and surrounding areas clean. We installed the parking lot in the center of the site also earlier than typical to prevent tracking of mud on the roadways and keep dust down. We are doing the best we can to stay good neighbors during this process.
 
Challenges of being able to procure materials due to the impact of the pandemic is a constant constraint on being able to perform at the level of efficiency that we are accustomed to. We have already started to compile a list of interested individuals, a majority who already live locally, who are wishing to lease a residence at Manor on the Green. That level of interest is a testament of how wonderful the New Town Community is. In addition, we have heard from many businesses in New Town inquiring about our completion as they are encouraged by the opportunity to be supported by these future residents.  